Incessant rain may hinder capping of Baghjan oil well

Pratidin Bureau

The Indian Army has joined Indian and foreign experts to draw out a detailed plan and control the flow of gas from the Baghjan oil well and cap it by July 7 after taking necessary precautions.

However, the operation seems uncertain due to the incessant rain across the state that has led to the incompletion of the road which would help Oil India Limited to resume their operations at the Baghjan Well Site Number 5.

The Indian Army completed the Pontoon bridge last week and is now assisting the civil administration and the public to rebuild the roads.

Walkable pathway to Debris area from the EPS side road along with railing is under preparation; about 1/3 completed.
Road maintanence work from Chakravorty Tiniali to Baba Tinali is in progress.
Repairing of road from Baba Tiniali to CMT pump
Repair of the road by laying water line near pump no.1
Road work continues amid adverse situations

Gauhati University Holds Session On Preparation For Civil Services

Assam Govt Announces Additional Grant To Majuli Raas Committees

Premier League: Liverpool Go Top With Brighton Win; City Lose To Bournemouth

"Baseless References": MEA To Canada Over Allegations Against Amit Shah

Manipur Police SI Shot Dead By Constable In Jiribam